Free The Sharon Construction Company Cases Study Case Studies Proposition 1 isn't perfect as it's the most costly. $20,000 prompting a multi week time spared doesn't give the organization the greatest advantages. The subsequent proposition is similarly costly since it is still unreasonably high for just sparing five weeks of the all out time. Doing nothing is certainly the most noticeably awful choice that can be taken since there are different prospects that are prominent. The fine for expansion week can't permit Jim to face the challenge since expecting that the strike and December is negative prompting an aggregate of about two months and a month individually would means over $120,000 in fines and another $60,000 on December. In any case, December may be unraveled by the exceptional warming. Material right on time at an extra expense of $9,000 and spare a month and a half is the best alternative. Such would provide food for conceivable awful climate in December and help decrease conceivable strike by about fourteen days.